Davidson Wood Phase 2



Project Status



Recent Updates (8/28/17)

The Construction Drawings for Phase 2 of Davidson Woods were approved by the Town and Mecklenburg County on 8/25/17; construction will begin in the near future, connecting to Bailey Springs until the bridge to the first phase of Davidson Wood is completed. 

  • When will erosion control installation take place? Scheduled 10/16/17 – 11/24/17
  • When will the parcel be cleared? Partial 10/1/17 – 10/27/17, remainder 11/27/17 – 1/5/18
  • How long do you anticipate construction to occur (to begin selling houses)? Phase 1 Land Development will take approximately 8 months.  Home construction will follow (4-5 months for first units coming online). See phasing plan here.


  1. Site Info
  2. Documents
  3. Contact

Site Info


  • Planning Area: Neighborhood General
  • Project Location: Davidson Hall Phase 2 is located at the southern terminus of Samuel Spencer Parkway
  • Parcel ID: 00709102
  • Acres: 32 +-
  • Development Description: A continuation of Davidson Wood Phase I, this is a single-family residential phase including 41 homes on 32 acres, with 14.21 acres of preserved open space (40% of site). Roadway connections are via Samuel Spencer Parkway, Park Terrace Lane and Bradford Park Drive. A greenway connection will also be provided to the Kincaid Trail from this phase of development.
  • Developer: Artisan Custom Homes